Warwick station subway reopens to passengers

By James Smith 23rd Jun 2025

Passengers at Warwick can now benefit from the newly reconstructed subway to make their way from platform one to two.

The subway, which had been closed since September 2024 as part of the station accessibility upgrades, reopened to passengers on Thursday (19 June).

Since spring 2024, Network Rail and its contractor have been on-site at Warwick station to install two new lifts, made possible by Government funding through the Access to All fund, which will help passengers with reduced mobility, families with prams, and those carrying heavy luggage access the two platforms.

Over the past 12 months, engineers have been working in the subway and station building, excavating land and installing over 50 piles across both platforms in readiness to install the new lifts.

The subway at Warwick Station reopened on Thursday 19 June (image via Network Rail)

While the subway was closed, it received its own upgrade, including a new entrance, handrails, steps, CCTV, security mirrors, lights, tactile paving, and cabling.

Joe Flynn, scheme project manager for Network Rail, said: "Work on the lift installation project is progressing really well, with both lift shafts now in place.

"I'm really pleased we've been able to reopen subway access from the main station entrance and I'd like to thank passengers for their patience while it has been closed.

"We're sorry for the disruption at the station but we're really looking forward to getting these lifts installed so that passengers can soon benefit from improved access to trains."

Attention now turns to the station entrance on the platform two side.

The subway has also been upgraded (image via Network Rail)

Engineers will be widening the doorway, replacing the steps, and installing a new ramp. The entrance from Platform two will need to be temporarily closed while work is continued this side of the station, so passengers will need to access the station from the main entrance on Station Road.

This next phase of the project follows the recent installation of the lift shaft on platform two.

At the beginning of June, engineers used a 450-tonne crane to impressively manoeuvre the lift shaft over the tracks and lower it into position, during the night while the railway was closed.

Lift shaft being craned over the track at Warwick station (image via Network Rail)

Daniel Gillard, area manager (Warwickshire), at Chiltern Railways, said: "I'm really pleased to see the newly reconstructed subway open to passengers again.

"This marks a key step forward in our commitment to making Warwick station more accessible and welcoming for everyone.

"These improvements will make a real difference for those travelling with mobility needs, luggage, or young children. Thank you to our customers for their patience while the work has been carried out, we're excited for the next stage of the project."

Passengers should check www.nationalrail.co.uk for the latest journey information and travel advice.

Works at Warwick Station have moved to platform two (image via Network Rail)

     

Please Support Us Warwick. Your Town. Your News. Your Support Matters.

Local news is essential for our community — but it needs your support.
By becoming a monthly supporter, you’ll help us continue delivering reliable local stories and events.
Your support makes a real difference to Warwick.
Monthly supporters will enjoy:
Ad-free experience

Share:


Sign-up for our FREE newsletter...

We want to provide warwick with more and more clickbait-free news.

     

...or become a Supporter.
Warwick. Your Town. Your News.

Local news is essential for our community — but it needs your support.
Your donation makes a real difference.
For monthly donators:
Ad-free experience