New lift shaft to be craned into place overnight at Warwick Railway Station

A pre-made lift shaft will be lifted into position at Warwick Railway Station next weekend as part of the ongoing work to improve passenger access.
The steel structure, which was manufactured off-site and delivered to the station last month, will be craned into position overnight on Saturday 7 June while the railway is closed and after the last train has passed through.
The lift shaft will be lifted over the tracks and lowered into place using a 450 tonne crane.
Network Rail and Chiltern Railways are advising passengers that during the unusual manoeuvre, for safety reasons, the car park will temporarily be closed on Saturday 7 June and until midday on Sunday 8 June.
There will be no pick-up or drop-off access after 5pm on Saturday (7 June) until midday on Sunday (8 June). Pedestrian access to platforms will not be affected.
Joe Flynn, scheme project manager for Network Rail, said: "Due to the limited space on platform 2, we've had to be creative with how we install this lift shaft. After pre-building the lift shaft off-site, we're now carefully moving it over the tracks at night when the railway is closed.
"This is a major milestone for the scheme and we thank passengers for their patience while the car park is closed to allow us access.
"We're sorry for the disruption at the station but we're really looking forward to getting these lifts installed so that passengers can soon benefit from improved access to trains."
Daniel Gillard, area manager (Warwickshire), at Chiltern Railways, said: "I would like to thank customers for their patience as Network Rail installs the lift shaft at Warwick, which is a key milestone towards improving accessibility at the station.
"To ensure customer safety while the lift shaft is installed, you will not be able to park at the station on Saturday (7 June) until midday on Sunday (8 June). There will also be no pick-up or drop-off access from 5pm on Saturday (7 June) until midday on the Sunday (8 June).
"Please make sure your plan your journey to the station ahead of travelling on those dates."
Network Rail and its contractor resumed work on-site at Warwick station in spring 2024 to install two new lifts which will help passengers with reduced mobility, families with prams, and those carrying heavy luggage access platforms 1 and 2.
Over the past 12 months, engineers have been working in the subway and station building, excavating land and installing over 50 piles across both platforms in readiness to install the new lifts.
Another key part of the project is work to the station subway.
The subway has been closed while engineers have been working in this area, with a diversion in place.
Network Rail plans to reopen the subway from platform 1 side mid-June. The entrance from Platform 2 will then need to be temporarily closed while work is continued that side of the station.
Share: