Green energy battery in Barford could store power for local network
By Harry Speirs 19th Nov 2026
Plans have been submitted to install a new battery storage facility on a grass verge beside the A429 in Barford.
Battery Box Limited, part of AMP Clean Energy, has applied to Warwick District Council for permission to install the facility on land east of the A429 and north of Westham Lane.
The proposed development would consist of a 200kW battery energy storage system, capable of storing 800kWh of electricity, alongside electrical equipment, a concrete foundation and a security fence.
The facility would occupy approximately 24 square metres – roughly the equivalent of two car parking spaces.
According to the planning statement, the battery would store electricity when demand is low or renewable energy generation is high, before releasing it back into the local electricity network during peak periods.
The applicant explained: "Each Battery Box connects directly to the local electricity network, from which it can import or export electricity."
It added that "the stored electricity would be exported and consumed locally, rather than being directly connected to existing wind or solar farms."
AMP Clean Energy estimates that each battery installation could save approximately 160 tonnes of carbon emissions annually and 4,800 tonnes over its lifetime.
Construction is expected to take approximately two weeks.
The facility would operate remotely, with visits only expected in response to faults or for maintenance.
The applicant states that noise from the proposed development "will have no significant impact" on the surrounding area.
The application also claims that only 24 square metres of grass would need to be removed.
The company argues that the installations will help support the UK's transition to renewable energy by storing surplus electricity and releasing it when demand increases.